When mixing and filling operate on different shifts, a line can be ready before the released product arrives. Start with the time the next batch is available and how much is usable. Ask what happens to the remaining product at the end of the filler shift.
Map a handoff across both teams
Record the mixing finish time, quality release, tank availability and filler demand. For illustration, 1,200 usable litres at 300 litres per hour provide four hours before the next lot. Confirm how pauses and other requirements change that window.
| Input or handoff | Example or evidence | Your shift |
|---|---|---|
| Released volume at start | 1,200 L | ___ |
| Filler consumption | 300 L/h | ___ |
| Usable production window | 4 hours | ___ |
| Next batch release | Time and named owner | ___ |
Prepare a handover between recipes
Review a line against your shift pattern
Send tank and batch capacities, release times and filler demand.